Saturday, June 24, 2017

Sea Trials and Spring Commissioning


Sea trials and spring commissioning took us more than one month. In that time, we got the engine up and running and did a number of sea trials to check on the engine mounts. Additionally, we had to commission the potable water system. It took some work to get all the antifreeze out of the tank.  We had to make a special fixture, connect it to a temporary hose, and use the manual pump installed at the forward sink (in the vanity area) to get the last 5 gallons (20 liters) out of the tank. Last year we cleaned and painted the water tank but there was a small area of the 80+ gallon (320+ liter) tank that we could not reach. As a result of the sediment hiding in this area of the tank, we ended up clogging three drinking water polishing filters and ended up installing a 20 micron pre-filter to remove coarse sediments. The water system is now working very well.
We also took the opportunity this spring to set up our reefing system for the main and mizzen sails as neither were yet operational. This involved drilling and riveting or tapping the booms and masts for both sails and installing blocks, cleats, and clutches for the reeling lines and main halyard.
Space on board is limited and over the winter we took time to remove approximately 150 lbs (70 kg) of extras that we did not want onboard. The extra volume below was very noticeable.  Stowing provisions and personal items this spring resulted in a much more comfortable arrangement in the main cabin, V-berth, and aft cabin.
So, after about six weeks, we finished provisioning, filled up with water, and we were ready to head out for a shakedown cruise. we hope you enjoy the pictures and artwork.

Dinghy on davits shortly after spring launch, Galesville, Maryland 
Reefed mizzen 
First sunset of the season - Galesville, Maryland 



First sunrise of the season - Galesville, Maryland







Wednesday, April 26, 2017

Winter Projects

The 2016/2017 winter in the Maryland was overall pretty mild and this worked to our advantage. We were able to work for most of the winter and by doing some woodworking at home during the days when temperatures were below 40F (4C) we were able to make great progress. From the end of December when we hauled and winterized Rosalind until the first week in April when we launched, we took the opportunity to spend some more time with friends and family and completed the following projects:

Windshield Wipers
We installed windshield wipers (this was on our to-do list after last year's shakedown cruise). We installed two wipers, one for the port window and one for the starboard window in the pilothouse (the opening middle window geometry does not lend itself to a wiper installation). We also fabricated a teak-faced box to accommodate the windshield wiper switches. The teak box, installed on the port side at the helm, has the same geometry as the one housing the depth finder on the starboard side.  We also installed a windshield washdown pump and reservoir and wired the pump to the new teak box. The plumbing for the system is in place however the spray nozzles are not installed yet. On the teak box we also added a USB charging port to facilitate the charging of iphones/iPads/etc. 

Starboard Windshield Wiper - from the Helm

Teak Box at the Helm

Electric Switches

110V Battery Charger and Cabin Heater Improvements
We installed a new battery charger with a remote controller/display and we used it over the winter to keep our batteries topped up. We also relocated the remote control panel for the Webasto cabin heater. Previously we had it secured in a small cardboard box until we found a permanent location for it. We also added a heater vent in the aft cabin and completed the installation of the V-berth vent. 

Cabin Heater and Battery Charger Controllers

Storm Anchor Storage
The two main components of our 75lb Luke storm anchor are now resting on custom made teak chocks on the top of the dorade box in front of the windshield. We found the location of the anchor pieces on deck, made mock-up chocks out of pine, then routed and fitted and through-bolted the teak blocks. Small cleats are used to secure the pieces on the chocks. 





Luke Storm Anchor Stock and Shank Secured in Teak Chocks

Teak Box for Electrical Switches
In the head, we made and installed a teak box to house two electrical switches for the main mast. One switch coverts the mast head light to a strobe (only to be used in emergencies) and the other activates the foredeck light. 
Teak Box for Main Mast Electrical Switches

Dinghy Davits
Throughout the winter we were on the lookout for warm days when we could do small epoxy jobs and at the very end of the winter, as the temperature started increasing, we finished the davits installation. The davits are placed outboard on the aft deck and the installation was very tight with clearances of well less than 1/4 inch at multiple places. In order to fit them, we built up the deck with fiberglass and made platforms that were not only flat on the top (for the davits to rest flat on them) but also at the proper angles for the davits to clear the stern seats and the cap rail. The davits were then through-bolted with backing plates to distribute the loads.  We have been very happy with the davits as they allow us to lift the dinghy out of the water (to prevent marine growth and discourage theft). An additional benefit of the davits is that they make boarding the dinghy much easier. 

Port Davit Installation - Done Under Winter Shrink Wrap

Dinghy on Davits

Dinghy on Davits - Looking Aft from the Cockpit

Painting Below Deck and Life Raft Storage
The aft cabin foot wells were painted just before launch and we found a new location to store the life raft. We also gave the head (bathroom) floor a much needed paint job.

Painted Foot Wells, Cabin Heater Exhaust (upper right)

Secured Life Raft

Freshly Painted Floor in Head Compartment

Deck Wash Pump
We installed a deck wash pump under the V-berth and connected it to the seacock and strainer for the head with a three-way valve.  We took advantage of a hole on deck left behind from an unused windlass foot operated switch, added a piece of teak to cover the hole, and used it to install the deck wash spigot. We have tried out the pump and works like a charm. Anchoring in mud will no longer require 20 to 30 buckets-full of water to rinse the anchor and chain! We will post a video clip of the pump in operation shortly.

We hope you enjoy the pictures. On the next blog post, we will go through our spring commissioning and sea trials. 

All the best,
Alex and Cheryl